www.trilliumsteel.ca Open in urlscan Pro
23.227.38.74  Public Scan

URL: https://www.trilliumsteel.ca/blogs/news/construction-costs-revealed
Submission: On January 06 via manual from US — Scanned from CH

Form analysis 4 forms found in the DOM

GET /search

<form action="/search" method="get" class="drawer__search" role="search">
  <input type="search" name="q" placeholder="Search" aria-label="Search" class="drawer__search-input">
  <button type="submit" class="text-link drawer__search-submit">
    <svg aria-hidden="true" focusable="false" role="presentation" class="icon icon-search" viewBox="0 0 32 32">
      <path fill="#444"
        d="M21.839 18.771a10.012 10.012 0 0 0 1.57-5.39c0-5.548-4.493-10.048-10.034-10.048-5.548 0-10.041 4.499-10.041 10.048s4.493 10.048 10.034 10.048c2.012 0 3.886-.594 5.456-1.61l.455-.317 7.165 7.165 2.223-2.263-7.158-7.165.33-.468zM18.995 7.767c1.498 1.498 2.322 3.49 2.322 5.608s-.825 4.11-2.322 5.608c-1.498 1.498-3.49 2.322-5.608 2.322s-4.11-.825-5.608-2.322c-1.498-1.498-2.322-3.49-2.322-5.608s.825-4.11 2.322-5.608c1.498-1.498 3.49-2.322 5.608-2.322s4.11.825 5.608 2.322z">
      </path>
    </svg>
    <span class="icon__fallback-text">Search</span>
  </button>
</form>

GET /search

<form action="/search" method="get" class="site-header__search small--hide" role="search">
  <label for="SiteNavSearch" class="visually-hidden">Search</label>
  <input type="search" name="q" id="SiteNavSearch" placeholder="Search" aria-label="Search" class="site-header__search-input">
  <button type="submit" class="text-link site-header__link site-header__search-submit">
    <svg aria-hidden="true" focusable="false" role="presentation" class="icon icon-search" viewBox="0 0 32 32">
      <path fill="#444"
        d="M21.839 18.771a10.012 10.012 0 0 0 1.57-5.39c0-5.548-4.493-10.048-10.034-10.048-5.548 0-10.041 4.499-10.041 10.048s4.493 10.048 10.034 10.048c2.012 0 3.886-.594 5.456-1.61l.455-.317 7.165 7.165 2.223-2.263-7.158-7.165.33-.468zM18.995 7.767c1.498 1.498 2.322 3.49 2.322 5.608s-.825 4.11-2.322 5.608c-1.498 1.498-3.49 2.322-5.608 2.322s-4.11-.825-5.608-2.322c-1.498-1.498-2.322-3.49-2.322-5.608s.825-4.11 2.322-5.608c1.498-1.498 3.49-2.322 5.608-2.322s4.11.825 5.608 2.322z">
      </path>
    </svg>
    <span class="icon__fallback-text">Search</span>
  </button>
</form>

GET /search

<form action="/search" method="get" class="site-header__search small--hide" role="search">
  <label for="SiteNavSearch" class="visually-hidden">Search</label>
  <input type="search" name="q" id="SiteNavSearch" placeholder="Search" aria-label="Search" class="site-header__search-input">
  <button type="submit" class="text-link site-header__link site-header__search-submit">
    <svg aria-hidden="true" focusable="false" role="presentation" class="icon icon-search" viewBox="0 0 32 32">
      <path fill="#444"
        d="M21.839 18.771a10.012 10.012 0 0 0 1.57-5.39c0-5.548-4.493-10.048-10.034-10.048-5.548 0-10.041 4.499-10.041 10.048s4.493 10.048 10.034 10.048c2.012 0 3.886-.594 5.456-1.61l.455-.317 7.165 7.165 2.223-2.263-7.158-7.165.33-.468zM18.995 7.767c1.498 1.498 2.322 3.49 2.322 5.608s-.825 4.11-2.322 5.608c-1.498 1.498-3.49 2.322-5.608 2.322s-4.11-.825-5.608-2.322c-1.498-1.498-2.322-3.49-2.322-5.608s.825-4.11 2.322-5.608c1.498-1.498 3.49-2.322 5.608-2.322s4.11.825 5.608 2.322z">
      </path>
    </svg>
    <span class="icon__fallback-text">Search</span>
  </button>
</form>

POST /blogs/news/construction-costs-revealed/comments#comment_form

<form method="post" action="/blogs/news/construction-costs-revealed/comments#comment_form" id="comment_form" accept-charset="UTF-8" class="comment-form"><input type="hidden" name="form_type" value="new_comment"><input type="hidden" name="utf8"
    value="✓">
  <h2 class="h3">Leave a comment</h2>
  <div class="grid grid--half-gutters">
    <div class="grid__item medium-up--one-half">
      <label for="CommentAuthor" class="label--hidden">Name</label>
      <input type="text" name="comment[author]" id="CommentAuthor" class="" placeholder="Name" value="">
    </div>
    <div class="grid__item medium-up--one-half">
      <label for="CommentEmail" class="label--hidden">Email</label>
      <input type="email" name="comment[email]" id="CommentEmail" class="" placeholder="Email" value="" autocorrect="off" autocapitalize="off">
    </div>
  </div>
  <label for="CommentBody" class="label--hidden">Message</label>
  <textarea name="comment[body]" id="CommentBody" class="" placeholder="Message"></textarea>
  <input type="submit" class="btn" value="Post comment">
  <p class="text-center"><small>Please note, comments must be approved before they are published</small></p>
</form>

Text Content

Skip to content
Search
 * Main
 * Products
   Barndominium Kits Custom Steel Buildings Accessories Soft Goods

 * Blog
 * About Trillium
 * FAQ
 * Connect
 * MIL/LEO/FR
 * 3D Barndominium Designer
 * Community Forum

Site navigation

Search Search
Cart
Menu Site navigation
 * Main
 * Products
   Barndominium Kits Custom Steel Buildings Accessories Soft Goods

 * Blog
 * About Trillium
 * FAQ
 * Connect
 * MIL/LEO/FR
 * 3D Barndominium Designer
 * Community Forum

Search Search
Cart
Item added to cart. View cart and check out. Close
Close

October 28, 2021


TWELVE.0 CONSTRUCTION COSTS REVEALED!

Hello Everyone!

We hope you found value in the previous newsletter on Vetting a Contractor but
If you missed it, we have uploaded it to our Blog found here!

We're answering the question that everyone has been asking... "How much can I
expect to spend on the construction of my kit?". Fortunately, we are here to
break down the costs that we have received from subcontractors to assist in your
budgeting. We will be reviewing our Flagship Twelve.0 kit for this review as we
are currently preparing to build a Twelve.0 model home which will be available
for tours shortly!

So…. let's get down to the brass tax!

1. Permits and Development fees - Yes, you need to pay them, no we don't know
how much they are. These fees vary depending on the municipality you are
planning to build in. We suggest reaching out to the Municipality and asking for
a copy of the permit and development fee schedule.

2. Site Preparation - Every Trillium kit requires the topsoil and all other
organic material (leaves, sticks, etc.) to be stripped where the foundation will
be placed. The amount of fill you will require will depend on how much grade
change your lot has. It's common for a project to take between 5 and 25 loads of
fill depending on the condition of our site and how much organics are removed.
In our area, a load of sand fill is approximately $250 delivered.

3. Plumbing - The plumbing costs received are between $10,000 and $21,000
depending on the scope of work. The $10,000 range allows you to pick and provide
your own fixtures for the plumber to install. Whereas the plumber will be
supplying and installing all the fixtures in the $21,000 range.

4. Final grading - Once the rough grading and the plumbing rough-in's are
complete (Plumbing rough-in video), you will require a minimum 6” of granular
“clear stone” to be spread and levelled. This is equivalent to two tandem dump
truck loads for the top layer at approximately $400 per load.

5. Floating Slab Installation - The pre-engineered floating slab kit that is
included in our package is incredibly easy to install, but some choose to have a
professional install it for them. The pricing for a contractor to construct the
slab kit including placing the insulation, supplying the concrete, and finishing
the concrete will be approximately $9,600.

6. Steel Structure Installation - The installation of the steel structure is
something a lot of our customers want to do themselves. If you are unable or do
not feel confident to complete this yourself and need to hire a professional,
you can expect to pay approximately $24,000 to have the structure erected with
the siding, roofing, windows, doors, trims, gutters, and downspouts installed.

7. Spray Foam Insulation - Spray foam prices are roughly $1.25 per square foot
per inch. Currently, the minimum code requirements for vaulted ceilings in
Ontario are R-20 for walls and R-31 for ceilings. This equates to approximately
$7,500 for the ceilings and $4,875 for the walls.

8. Interior Framing - Once the structure is erected and the spray foam
insulation is placed, it's time to frame out the inside of the home. The cost of
the wood studs as well as installation will be approximately $15,000.

9. Electrical - We have received several quotes on this ranging between $15,000
and $20,000 depending on certain requests such as pot lights, generators, solar,
and more. The servicing from the road or well and septic system will be an added
expense that will need to be confirmed with the Municipality or a well and
septic installer in your area.

10. Drywall - The Trillium TWELVE.0 will require approximately 5,000 square feet
of drywall. You can expect to pay between $1.80 and $3.50 per square foot to
have someone supply and install the drywall. This fee includes taping the seams,
plastering and sanding. Using midrange pricing the drywall should cost
approximately $13,500.

11. Mechanical - On our website you have the option to upgrade from a
conventional forced air heating and air conditioning system with HRV to a
hydronic heated floor system and utilize a ductless mini-split with modular HRV
system. The cost for the conventional system is approximately $16,500 and this
covers the furnace, air conditioning, HRV unit and ductwork. The combination
boiler option (capable of both heating your floors as well as giving you hot
water on demand) with modular HRV system and ductless air conditioning system
will cost approximately $24,000 not including the cost of the hydronic
preparation package (available on our website).

12. Trim - the entire trim package for a TWELVE.0 can be had for very little
money. A mid-range trim package is going to cost approximately $3,000 for the
entire home.

13. Paint - We are sure that most of our customers are going to be painting
themselves, but here are the associated costs. You're going to need to budget
approximately $1,500 for paint and supplies, or be prepared to pay for a
professional painter at approximately $6,000 to complete the job for you.

14. Kitchen - This can be as custom or as simple as you want. You can obtain
quotes from custom kitchen cabinet makers or price out a kitchen from Ikea and
assemble it yourself. For a kitchen in the Twelve.0 you can expect to pay
between $5,000 (from Ikea) and $15,000 for a custom kitchen. In addition to the
kitchen cabinets, you will need countertops. Again, you could install a higher
end granite, quartz or marble or a simple laminate countertop and could expect
to pay between $500 and $3,500. 


Our intentions when designing our kits was to provide our customers with a turn
key home design for under $200 per square foot and as you can see, we have
surpassed this. The total value can be greatly reduced depending on how much you
can complete yourself, and as an example we are currently completing a live cost
analysis on a Twelve.0 and expect it to come in under $150 per square foot or
under $180,000. That’s right, a full home build with construction costs under
$200,000, in the most expensive building era in history!

Thanks for sticking with us and our boring newsletters so far. Next week we are
going to be discussing what's included "in-the-box" and how the process from
ordering your kit to the delivery is completed.

-- Eric & Kyle

--------------------------------------------------------------------------------

Share
Share on Facebook Tweet on Twitter Pin on Pinterest


LEAVE A COMMENT

Name
Email
Message

Please note, comments must be approved before they are published


Back to News

MENU

 * Search
 * Your Privacy
 * Terms & Conditions
 * Careers
 * Terms of Service
 * Refund policy

SHOP

 * Barndominium Kits
 * Garage Packages
 * Accessories
 * Soft Goods

BLOG

 * Blog
 * About Us

FOLLOW US

 * Facebook
 * Pinterest
 * Instagram
   
 * YouTube

CONNECT

By Phone:
1-226-BARNDOS (227-6367)
By Email: Info@trilliumsteel.com
3232 Goldstein Road
Washago, ON. L0K 2B0

Payment methods
 * American Express
 * Discover
 * Mastercard
 * Shop Pay
 * Visa

 * Choosing a selection results in a full page refresh.
 * Press the space key then arrow keys to make a selection.
 * Use left/right arrows to navigate the slideshow or swipe left/right if using
   a mobile device








SUBSCRIBE